Latest Updates

Date

Description

16 May 2013New Photos added for Surabaya, Java - Excavation work ongoing after completion of sheet piling
15 May 2013New Photos added for Quezon City, Manila - Roof deck being prepared for concrete works. Builderswork and MEP continuing to lower floors
14 May 2013New Photos added for ASEANA City, Manila - Excavation works to expose piles underway along with site set up
13 May 2013New Photos added for Bekasi, Jakarta - Roof deck slab preparation underway. Builderswork continuing on lower floors
10 May 2013New Photos added for Cagayan de Oro, Mindanao - Builderswork and MEP progressing to top floors with finishing works continuing on all other floors
09 May 2013New Photos added for Solo City, Java - Builderswork and MEP progressing to all floors
08 May 2013New Photos added for Davao City - 5th floor slab being prepared for concrete pour
07 May 2013New Photos added for Makassar, Sulawesi - Contractor remobilizing to site
03 May 2013New Photos added for Ortigas, Manila - 5th floor preparation for concrete pour completing
02 May 2013New Photos added for Quezon City, Manila - 11th floor being prepared for concrete works. Builderswork and MEP started to lower floors
30 April 2013New Photos added for Bekasi, Jakarta - Part 7th floor slab being prepared for concrete pour. Builderswork continuing on lower floors
29 April 2013New Photos added for Surabaya, Java - Excavation work under way after completion of sheet piling
26 April 2013New Photos added for Cagayan de Oro, Mindanao - Builderswork and MEP progressing to top floors with finishing works continuing on all other floors
25 April 2013New Photos added for Quezon City, Manila - 10th floor being prepared for concrete works. Builderswork started to lower floors
24 April 2013New Photos added for Bekasi, Jakarta - Part 6th floor slab being prepared for concrete pour. Builderswork started on lower floors
23 April 2013New Photos added for Davao City - 4th floor slab being prepared for concrete pour
22 April 2013New Photos added for Solo City, Java - Builderswork and MEP progressing to all floors.
12 April 2013New Photos added for Palembang, Indonesia - Piling complete, pile capping progressing onsite
11 April 2013New Photos added for Davao City - Remainder of 2nd floor slab being prepared for concrete pour
10 April 2013New Photos added for Solo City, Java - Builderswork and MEP progressing to all floors. Mock up room underway
09 April 2013New Photos added for Bekasi, Indonesia - Part 5th floor slab being prepared for concrete pour
05 April 2013New Photos added for Surabaya, Java - Dewatering and cleaning continuing onsite
04 April 2013New Photos added for Quezon City, Manila - Concrete works at 7th floor level
03 April 2013New Photos added for Cagayan de Oro, Mindanao - MEP, builderworks and finishing works progressing
02 April 2013New Photos added for Ortigas, Manila - Third floor slab concrete works progressing
29 March 2013New Photos added for Davao City - Part second floor slab being prepared for concrete pour
28 March 2013New Photos added for Mall of Asia, Manila - Piling complete
27 March 2013New Photos added for Bekasi, Jakarta - Part 3rd floor slab poured
22 March 2013New Photos added for Surabaya, Java - Piling progressing onsite
21 March 2013New Photos added for Quezon City, Manila -5th Floor being prepared for concrete pour
20 March 2013New Photos added for Cagayan de Oro, Mindanao - Builderswork and MEP progressing to all floors. Finishing works continuing on lower floors
19 March 2013CSR activity from Tune Ermita: Cleaning of Rajah Sulaiman Park and Mabini Street, tree-planting at Bahay Punlaan, Lumban Laguna.
19 March 2013CSR activity from Tune Cebu: Tree-Planting, clean-up drive, and mural painting at Cebu City Zoo with the City Government and Haribon Foundation.
19 March 2013CSR activity from Tune Makati: Clean-Up Drive in Barangay Poblacion, Makati City with the Clean & Green Committee of Barangay Poblacion.
19 March 2013CSR activity from Tune Angeles: Repainting of Sta. Teresita Elementary School in Angeles, Pampanga and tree-planting at Palauig, Zambales.
19 March 2013CSR activity from Tune Pasar Baru: Cleaning up of Passer Baroe Shopping Area.
19 March 2013CSR activity from Tune Pekanbaru: Cleaning around Masjid Agung and donate additional waste bins to support keeping Pekanbaru beautiful and clean.
19 March 2013New Photos added for Ortigas, Manila - Second floor slab part poured and final part being prepared
18 March 2013Tune Hotel Pattaya CSR Activity - Collect the rubbishes on the Pattaya beach
18 March 2013Tune Hotel Patong, Phuket CSR Activity - Keep our beach clean
18 March 2013Tune Hotel Hat Yai CSR Activity - Tree Planting at Lam-Son-on, Songkhla Lake
18 March 2013Tune Hotel Asoke CSR Activity - Painting Heath and Development Centre in the Bon Kai community
18 March 2013New Photos added for Pekanbaru, Indonesia - Tune Pekanbaru opens and welcomes its first guest on 18 March 2013
15 March 2013New Photos added for Mall of Asia, Manila - Piling works ongoing
14 March 2013New Photos added for Solo City, Java - Builderswork and MEP progressing to all floors
13 March 2013New Photos added for Davao City, Philippines - Part ground floor suspended slab poured
12 March 2013New Photos added for Palembang, Indonesia - Piling works ongoing
11 March 2013New Photos added for Bekasi, Indonesia - Concrete being poured to part first floor slab
07 March 2013New Photos added for Quezon City, Manila - 3rd floor concrete poured to Southside and being prepared for remainder of floor
06 March 2013New Photos added for Pekanbaru, Indonesia - Lower floors complete and finishing to upper floors nearing to completion
05 March 2013New Photos added for Cagayan de Oro, Mindanao - Mock up rooms complete. Builderswork and MEP progressing to all floors.
04 March 2013New Photos added for Ortigas, Manila - Below ground structural works progressing completing and ground floor slab being prepared
01 March 2013New Photos added for Solo City, Java - Building Structure complete. Builderswork and MEP progressing to all floors
28 February 2013New Photos added for Makassar, Sulawesi - 5th floor concrete slab being prepared
27 February 2013New Photos added for Surabaya, Java - Piling progressing onsite
21 February 2013New Photos added for Bekasi, Jakarta - Excavation and foundation works progressing
20 February 2013New Photos added for Quezon City, Manila - 2nd floor concrete pour being completed
19 February 2013New Photos added for Palembang, Sumatra - Piling works ongoing
18 February 2013New Photos added for Davao City - Foundation concrete works being prepared
07 February 2013New Photos added for Pekanbaru, Indonesia - Finishes at lower floors being closed out and continuing on upper floors
06 February 2013New Photos added for Solo City, Java - Level 9 concrete pour progressing and MEP works progressing on floors below
05 February 2013New Photos added for Cagayan de Oro, Mindanao - Concrete pour for roof slab being made ready. Mock up room completing
04 February 2013New Photos added for Ortigas, Manila - Below ground structural works progressing
31 January 2013New Photos added for Makassar, Sulawesi - Level 4 slab poured and MEP works progressing
30 January 2013New Photos added for Quezon City, Manila - Below ground concrete works progressing
29 January 2013New Photos added for Palembang, Sumatra - Piling works ongoing
28 January 2013New Photos added for Davao City - Excavation works continuing and concreting works progressing
25 January 2013New Photos added for Pekanbaru, Indonesia - Finishes at lower floors being closed out and continuing on upper floors
24 January 2013New Photos added for Ortigas, Manila - Below ground structural works progressing
23 January 2013New Photos added for Solo City, Java - Level 8 preparation for concrete pour progressing and MEP works progressing
22 January 2013New Photos added for Cagayan de Oro, Mindanao - Internal builderswork and MREP works progressing. Building at top floor slab
21 January 2013New Photos added for Bekasi, Jakarta - Excavation and main building preparation works progressing
17 January 2013
16 January 2013New Photos added for Quezon City, Manila - Below ground works progressing
15 January 2013New Photos added for Makassar, Sulawesi - Preparation for Level 4 slab underway
14 January 2013New Photos added for Palembang, Sumatra - Piling works ongoing
09 January 2013New Photos added for Bekasi, Jakarta - Pile driving works ongoing
08 January 2013New Photos added for Solo City, Java - Level 7 concrete works preparation works underway
07 January 2013New Photos added for Ortigas, Manila - Below ground structural works underway
28 December 2012New Photos added for Makassar, Sulawesi - Level 2 slab concrete pouring underway
27 December 2012New Photos added for Pekanbaru, Indonesia - Finishes works underway
26 December 2012New Photos added for Davao City, Site establishment and site clearing works progressing
20 December 2012New Photos added for Bekasi, Jakarta - Pile driving works commenced
19 December 2012New Photos added for Solo City, Java - Level 5 concrete works be made ready for concrete pour
18 December 2012New Photos added for Cagayan de Oro, Mindanao - Zone 1 and Zone 2 Concrete slab works progressing and nearing top level
17 December 2012New Photos added for Ortigas, Manila - Excavation works progressing
14 December 2012New Photos added for Patong, Phuket - Lobby interior fit -out works nearing completion
13 December 2012New Photos added for Makassar, Sulawesi - Level 1 slab zone 2 being prepared for concrete pour
12 December 2012New Photos added for Pekanbaru, Indonesia - Builderswork, MEP and Finishes work progressing
11 December 2012New Photos added for Davao City, MindanaoDemolition and site set up progressing
04 December 2012New Photos added for Bekasi, Jakarta - Contractor site establishment underway
03 December 2012New Photos added for Cagayan de Oro, Mindanao - Zone 1 and Zone 2 Concrete slab works progressing
30 November 2012New Photos added for Makassar, Sulawesi - Lower structure works ongoing
29 November 2012New Photos added for Solo City, Java - Level 3 concrete works be made ready for concrete pour
27 November 2012New Photos added for Patong, Phuket - Exterior building paint started and main lobby fit-out work in progress
08 November 2012New Photos added for Makassar, Sulawesi - Pile Caps and Ground Beams Being Completed
07 November 2012New Photos added for Solo City, Java - Ground Floor Columns Complete and First Upper Floor Slabs Being Cast
06 November 2012New Photos added for Patong, Phuket - External plastering in progress. Internal finishing works on 2nd floor nearing completion
31 October 2012New Photos added for Pekanbaru, Indonesia - MEP, builderswork work continuing to progress internally. Mock up room complete
30 October 2012New Photos added for Cagayan de Oro, Mindanao - Part of 5th floor being prepared for concrete pour
26 October 2012New Photos added for Patong, Phuket - External blockwall completed and plaster work commencing
25 October 2012New Photos added for Solo City, Java - Part ground floor slab being prepared for concrete pour
24 October 2012New Photos added for Makassar, Sulawesi - Foundation concrete works ongoing
17 October 2012New Photos added for Pekanbaru, Indonesia - MEP, Builderswork work continuing to progress internally
16 October 2012New Photos added for Cagayan de Oro, Mindanao - Part of third floor being prepared for concrete pour
10 October 2012New Photos added for Patong, Phuket - Mock up rooms completed and inspected. Partition and tiling works are underway towards completion
09 October 2012New Photos added for Solo City, Java - Foundation and basement concrete works progressing
08 October 2012New Photos added for Makassar, Sulawesi - Foundation work ongoing
03 October 2012New Photos added for Pekanbaru, Indonesia - MEP, Builderswork work continuing to progress internally
02 October 2012New Photos added for Cagayan de Oro, Mindanao - Structure work continuing to basement level
27 September 2012New Photos added for Patong, Phuket - Structure has been topped off, mock up rooms nearing completion
26 September 2012New Photos added for Solo City, Java - Foundation works now progressing
25 September 2012New Photos added for Makassar, Sulawesi - Foundation work ongoing
25 September 2012New Photos added for Mall of Asia, Manila - Site Acquisition
19 September 2012New Photos added for Makassar, Sulawesi - Foundation work ongoing
18 September 2012New Photos added for Pekanbaru, Indonesia - MEP, Builderswork work progressing internally
17 September 2012New Photos added for Cagayan de Oro, Mindanao - Structure work to basement level continues
12 September 2012New Photos added for Asoke, Bangkok - Monks blessing the hotel for good fortune and success. Staff excited and ready for welcoming guests on the 14th
12 September 2012New Photos added for Patong, Phuket - Building structure is progressing to level 7 and mock up rooms in progress
11 September 2012New Photos added for Asoke, Bangkok - Hotel completed and ready for opening on 14 September 2012
10 September 2012New Photos added for Solo City, Java - Excavation work continuing onsite to expose pile heads
05 September 2012New Photos added for Makassar, Sulawesi - Foundation work ongoing
04 September 2012New Photos added for Pekanbaru, Indonesia - MEP, Builderswork work progressing internally. Top floor slab complete
03 September 2012New Photos added for Pasar Baru, Jakarta - Tune Pasar Baru Launched in Jakarta with special guests: Movie star Nicholas Saputra, Mark Lankester CEO of Tune Hotels, model Isabel Yahya, and Ken Kerr from Red Planet Hotels
03 September 2012New Photos added for Cagayan de Oro, Mindanao - Columns continuing to be prepared for concrete pour
29 August 2012New Photos added for Patong, Phuket - Slab structure concrete progressing to level 5th and mock up rooms started
28 August 2012New Photos added for Asoke, Bangkok - Most guestrooms completed. Main lobby fit-out nearing completion
22 August 2012New Photos added for Cagayan de Oro, Mindanao - Columns being prepared for concrete pour
21 August 2012New Photos added for Solo City, Java - Columns being prepared for concrete pour
20 August 2012New Photos added for Makassar, Sulawesi - Foundations being completed
17 August 2012New Photos added for Patong, Phuket - Concrete slab progressing to level 4
16 August 2012New Photos added for Asoke, Bangkok - Main Lobby 90% completed. External building under final painting
15 August 2012New Photos added for Cagayan de Oro, Mindanao - Pile caps being poured
14 August 2012New Photos added for Makassar, Sulawesi - Pilecaps works continuing
09 August 2012New Photos added for Solo City, Java - Excavation for pile caps progressing
08 August 2012New Photos added for Pekanbaru, Indonesia - 8th floor concrete slab preparation works underway. MEP and builderswork work progressing to lower floors
01 August 2012New Photos added for Asoke, Bangkok - 2nd floor finishing works are nearly completed and Main Lobby decoration is on progress
31 July 2012New Photos added for Patong, Phuket - 2nd floor concrete slab has been done
30 July 2012New Photos added for Makassar, Sulawesi - Pilecaps works continuing
23 July 2012New Photos added for Pekanbaru, Indonesia - 6th floor concrete slab completing. MEP and internal builderswork commenced to below floors
18 July 2012New Photos added for Patong, Phuket - Tower crane erected, ground floor slab casting in progress
17 July 2012New Photos added for Asoke, Bangkok - Overall interior works progressing
16 July 2012New Photos added for Makassar, Sulawesi - Preparing for pilecaps
11 July 2012New Photos added for Solo City, Java - Piling works continuing
10 July 2012New Photos added for Pekanbaru, Indonesia - 5th floor concrete slab being prepared
09 July 2012New Photos added for Pasar Baru, Jakarta - Final preperation underway for the opening of our newest hotel in Jakarta. We look forward to welcoming our first guest this Thursday!
03 July 2012New Photos added for Makassar, Sulawesi -Excavation work to expose and cut pile heads underway
02 July 2012New Photos added for Pasar Baru, Jakarta - Interior finishing work nearing completion
28 June 2012New Photos added for Asoke, Bangkok - Electric transformer installed onsite, external drainage pipe work in progress
27 June 2012New Photos added for Makati, Manila - Interior finishing works completing
26 June 2012New Photos added for Solo City, Java - Piling underway
25 June 2012New Photos added for Pekanbaru, Indonesia - 4th floor concrete slab works underway
22 June 2012New Photos added for Patong, Phuket - Underground water tank concreting completed and backfilled
21 June 2012New Photos added for Pasar Baru, Jakarta - Interior finishing work progressing
20 June 2012New Photos added for Makassar, Sulawesi - Setting out commenced
14 June 2012New Photos added for Pekanbaru, Indonesia - Second floor concrete slab works underway
13 June 2012New Photos added for Makati, Manila - Interior finishing works nearing completion
12 June 2012New Photos added for Asoke, Bangkok - External and internal wall plastering in progress
07 June 2012New Photos added for Patong, Phuket - Site Demolition Nearing Complete
06 June 2012New Photos added for Pasar Baru, Jakarta - Interior finishing work progressing
05 June 2012New Photos added for Makassar, Sulawesi - Site set up nearing completion
30 May 2012New Photos added for Asoke, Bangkok - Building structure completed. Unit block walling with M&E piping progressing to 5th floor
29 May 2012New Photos added for Makati, Manila - Internal finishes works progressing
28 May 2012New Photos added for Pekanbaru, Sumatra - Part of first floor slab being prepared for concrete pour
23 May 2012New Photos added for Patong, Phuket - Excavation works for substructure in progress
22 May 2012New Photos added for Pasar Baru, Jakarta - Interior finishing work progressing
21 May 2012New Photos added for Makassar, Sulawesi - Site set up for main works underway
17 May 2012New Photos added for Makati, Manila - Internal finishes works progressing
16 May 2012New Photos added for Pekanbaru, Indonesia - Basement construction wall construction continuing
15 May 2012New Photos added for Asoke, Bangkok - Roof concrete slab completed and main equipment delivered to site
09 May 2012New Photos added for Patong, Phuket - Piling complete, excavation for substructure work commences
08 May 2012New Photos added for Pasar Baru, Jakarta - Interior finishing work progressing
02 May 2012New Photos added for Pekanbaru, Indonesia - Concreting works to lower floor progressing
30 April 2012New Photos added for Asoke, Bangkok - Main structure works progressing. Mock up room nearing completion
25 April 2012New Photos added for Patong, Phuket - Piling works 90% complete
24 April 2012New Photos added for Makati, Manila - Finishing works/ trades progressing
23 April 2012New Photos added for Pasar Baru, Jakarta - Interior finishing work progressing
20 April 2012New Photos added for Pekanbaru, Indonesia - Building frame reinforcement being prepared
18 April 2012New Photos added for Asoke, Bangkok - Mock up room completing
12 April 2012New Photos added for Patong, Phuket - Piling works 80% complete
10 April 2012New Photos added for Makati, Manila - MEP works continuing with finishes about to commence
04 April 2012New Photos added for Asoke, Bangkok - Mock up room nearing completion. Congrete slap progressing to 7th floor
03 April 2012New Photos added for Pasar Baru, Jakarta - Internal plasterwork and MEP works progressing
02 April 2012New Photos added for Pekanbaru, Indonesia - Preparation works for concrete foundations progressing
27 March 2012New Photos added for Patong, Phuket - Piling nearing completion, Site office now set up
26 March 2012New Photos added for Makati, Manila - Plastering works continuing to external face of building
21 March 2012New Photos added for Asoke, Bangkok - Concrete slab progressing, mock-up rooms wall started
20 March 2012New Photos added for Pekanbaru, Indonesia - Pile cap work completing
19 March 2012New Photos added for Pasar Baru, Jakarta -Builderswork and MEP ongoing
14 March 2012New Photos added for Makati, Manila - Buildersworks and MEP ongoing
13 March 2012New Photos added for Makassar, Sulawesi - Piling works ongoing. Water being pumped out of site
09 March 2012New Photos added for Ermita, Manila - Opening Ceremony at Tune Ermita, Manila
08 March 2012New Photos added for Patong, Phuket - Piling work ongoing
07 March 2012New Photos added for Asoke, Bangkok - Concrete floor slab in progress
06 March 2012New Photos added for Pekanbaru, Indonesia - Pile caps and ring beams being formed
05 March 2012New Photos added for Pasar Baru, Jakarta - Mock up Room Completing. MEP and Builderswork progressing
01 March 2012New Photos added for Makassar, Sulawesi - Piling work ongoing
29 February 2012New Photos added for Makati, Manila - Building structure completing with builderswork and MEP works progressing
28 February 2012New Photos added for Ermita, Manila - Internal finishing works progressing. External works nearing completion
27 February 2012New Photos added for Cagayan de Oro, Mindanao - Piling Works Complete
23 February 2012New Photos added for Asoke, Bangkok - First floor slab concrete ongoing
22 February 2012New Photos added for Patong, Phuket - Piling work progressing
21 February 2012New Photos added for Pekanbaru, Indonesia - Tower crane being erected and excavation works progressing
20 February 2012New Photos added for Pasar Baru, Jakarta -Builderswork and MEP first fix progressing
17 February 2012New Photos added for Pattaya, Chonburi - The Mayor of Pattaya City
16 February 2012New Photos added for Makati, Manila - Builderswork, MEP and top floor slab completing. Mock up room progressing
15 February 2012New Photos added for Ermita, Manila - External and internal finishing works closing out
14 February 2012New Photos added for Cebu City, Cebu - Classroom training for Cebu team
13 February 2012New Photos added for Patong, Phuket - Piling Works Progressing Onsite
10 February 2012New Photos added for Angeles City, Pampanga - Getting ready for Angeles opening
09 February 2012New Photos added for Asoke, Bangkok - 1st floor slab ongoing
08 February 2012New Photos added for Pattaya, Chonburi - Main Lobby and External Building completed
07 February 2012New Photos added for Pekanbaru, Indonesia - Ground works progressing
06 February 2012New Photos added for Pasar Baru, Jakarta - Internal Builderworks and mock up room works progressing
02 February 2012New Photos added for Angeles City, Pampanga - External and finishing works progressing
01 February 2012New Photos added for Makati, Manila - 9th floor being prepared for concrete pour. Builderswork and Mock up room progressing
31 January 2012New Photos added for Cebu City, Cebu - External and finishing works progressing
30 January 2012New Photos added for Ermita, Manila - External and finishing works progressing
26 January 2012New Photos added for Pekanbaru, Indonesia - Soil retaining works commenced
25 January 2012New Photos added for Pasar Baru, Jakarta - Internal MEP and Builderswork progressing. Roof slab being readied for concrete pour
24 January 2012New Photos added for Pattaya, Chonburi - External Works and Internal Finishing progressing to completion
23 January 2012New Photos added for Asoke, Bangkok - Basement works continuing onsite
19 January 2012New Photos added for Cagayan de Oro, Mindanao - Piling works commenced onsite
18 January 2012New Photos added for Ermita, Manila - Finishing works progressing
17 January 2012New Photos added for Cebu City, Cebu -Finishing works progressing
16 January 2012New Photos added for Angeles City, Pampanga - Interior finishes progressing
10 January 2012New Photos added for Asoke, Bangkok - First floor slab in progress
09 January 2012New Photos added for Pattaya, Chonburi - External Works progressing
06 January 2012New Photos added for Cebu City, Cebu - Builderswork and finishing works progressing
05 January 2012New Photos added for Angeles City, Pampanga - Exterior Painting works and interior finishes progressing
29 December 2011New Photos added for Pekanbaru, Indonesia - Piling complete and site prepared for main works to commence
28 December 2011New Photos added for Pasar Baru, Jakarta - Concrete floor slab to 5th floor complete
27 December 2011New Photos added for Pattaya, Chonburi - Internal finishing work progressing
26 December 2011New Photos added for Asoke, Bangkok - Basement works nearing completion
22 December 2011New Photos added for Ermita, Manila - Building watertight and internal finishing work progressing
21 December 2011New Photos added for Cebu City, Cebu - Internal finishing work progressing
20 December 2011New Photos added for Makati, Manila - 6th floor concrete slab works ongoing
19 December 2011New Photos added for Angeles City, Pampanga - Internal finishing work progressing
16 December 2011New Photos added for Hat Yai, Songkhla - Tune Hotel Hat Yai Opens
16 December 2011New Photos added for Pattaya, Chonburi - Internal finishing works progressing
15 December 2011New Photos added for Asoke, Bangkok -Basement works concreting progressing
14 December 2011New Photos added for Pasar Baru, Jakarta - 4th floor concrete slab completed
09 December 2011New Photos added for Cebu City, Cebu - Mock Up complete and internal works progressing
08 December 2011New Photos added for Ermita, Manila - Internal finishing works progressing
08 December 2011Red Planet closes on a hotel development in Tangerang, Jakarta
07 December 2011New Photos added for Angeles City, Pampanga - Façade Painting works started and internal MEP and finishes work ongoing
30 November 2011New Photos added for Hat Yai, Songkhla - Tune Hotels logos on the front building elevation have been installed
29 November 2011New Photos added for Pattaya, Chonburi - Main services equipment installation in progress
28 November 2011New Photos added for Asoke, Bangkok - Ongoing building foundation work
24 November 2011New Photos added for Pasar Baru, Jakarta - Concrete slab works to second floor progressing
23 November 2011New Photos added for Cebu City, Cebu - Mock up room completing and exterior blockwork progressing
22 November 2011New Photos added for Ermita, Manila - Internal finishing works progressing
21 November 2011New Photos added for Angeles City, Pampanga - MEP works progressing and internal finishing underway
16 November 2011New Photos added for Hat Yai, Songkhla - Façade works 90% complete and interior finishing works progressing
15 November 2011New Photos added for Pattaya, Chonburi - Internal finishing works ongoing
14 November 2011New Photos added for Asoke, Bangkok - Piling complete and basement works underway
10 November 2011New Photos added for Pekanbaru, Indonesia - Piling Works Progressing Onsite
09 November 2011New Photos added for Cebu City, Cebu - Building structure nearing completion. Mock up rooms being prepared
08 November 2011New Photos added for Angeles City, Pampanga -Internal builderswork and MEP progressing
07 November 2011New Photos added for Ermita, Manila - Internal finishing work progressing
03 November 2011New Photos added for Pasar Baru, Jakarta - Preparation for Concrete Works on Ground Floor Level Underway
02 November 2011New Photos added for Asoke, Bangkok - Excavation work progressing
01 November 2011New Photos added for Hat Yai, Songkhla - Finishing work progressing
31 October 2011New Photos added for Pattaya, Chonburi - Internal finishing works ongoing
28 October 2011New Photos added for Ermita, Manila - Internal works ongoing with finishing works started
27 October 2011New Photos added for Cebu City, Cebu - Structure works to level 9 complete"
26 October 2011New Photos added for Angeles City, Pampanga - Building structure 99% complete and internals works progressing
25 October 2011New Photos added for Ortigas, Manila - Demolition works in progress
20 October 2011New Photos added for Pasar Baru, Jakarta - Basement works progressing
19 October 2011New Photos added for Hat Yai, Songkhla - Finishing work progressing and front building facade
18 October 2011New Photos added for Asoke, Bangkok - Ongoing process of underground substructures work
17 October 2011New Photos added for Pattaya, Chonburi - Overall building structure completed
12 October 2011New Photos added for Ermita, Manila - Mock up room completed
11 October 2011New Photos added for Cebu City, Cebu - Concreting Works on 7th and 8th floor
10 October 2011New Photos added for Angeles City, Pampanga - Mock up room completed
06 October 2011Red Planet closes on a hotel development in Solo City, Java
06 October 2011New Photos added for Asoke, Bangkok - Piling work completed & foundation works commence
05 October 2011New Photos added for Hat Yai, Songkhla - Facade work commences and interior works progressing
04 October 2011New Photos added for Pattaya, Chonburi - Mock up room completed
03 October 2011New Photos added for Pasar Baru, Jakarta - Concrete columns from basement level being formed
30 September 2011New Photos added for Cebu City, Cebu - Floor slab preparation works on 6th floor
29 September 2011New Photos added for Angeles City, Pampanga - Level 9 floor slab works progressing
28 September 2011New Photos added for Makati, Manila - Works progressing to 4th floor level
27 September 2011New Photos added for Ermita, Manila - Structural works complete and internal work progressing
22 September 2011New Photos added for Hat Yai, Songkhla - Tune Approves Mock Up Room in Hat Yai on First Inspection
22 September 2011Red Planet closes on a hotel development in Bekasi, Jakarta
21 September 2011New Photos added for Pasar Baru, Jakarta - Concreting Works on Basement Level
20 September 2011New Photos added for Pattaya, Chonburi - Concrete slab progressing on roof level
19 September 2011New Photos added for Asoke, Bangkok - Piling works 95% complete, excavation works commence
15 September 2011New Photos added for Makati, Manila - First Floor Columns Being Poured
14 September 2011New Photos added for Angeles City, Works progressed to 8th floor level
13 September 2011New Photos added for Cebu City, Cebu - Works progressed to 4th floor level
12 September 2011New Photos added for Ermita, Manila - Roof Slab Complete and Parapet Works Ongoing
08 September 2011Red Planet closes on a hotel development in Davao City, Mindanao
07 September 2011New Photos added for Hat Yai, Songkhla - Refurbishment Works Continue
06 September 2011New Photos added for Pattaya, Chonburi - Concrete Slab Progressing on 7th Floor
05 September 2011New Photos added for Asoke, Bangkok - Piling Work Now 65% Complete
01 September 2011New Photos added for Makati, Manila - Further Floor Slabs Being Prepared for Concrete Pours
31 August 2011New Photos added for Ermita, Manila - Building Structure Works Continuing to Complete
30 August 2011New Photos added for Cebu City, Cebu - Concrete Slab Works Progressing on 3rd Floor
29 August 2011New Photos added for Angeles City, Pampanga - 7th Floor Concrete Works Now Completing
24 August 2011New Photos added for Pasar Baru, Jakarta - Basement Excavation and Substructure Works Underway
23 August 2011New Photos added for Asoke, Bangkok - Piling Work Now 35% Complete
22 August 2011New Photos added for Pattaya, Chonburi - Concrete Works Progressing on 5th Floor
19 August 2011New Photos added for Angeles City, Pampanga - Structural Work to 5th Floor Level
19 August 2011New Photos added for Angeles City, Pampanga - Structural Work to 5th Floor Level
18 August 2011New Photos added for Makati, Manila - First Floor Slab Ongoing
17 August 2011New Photos added for Cebu City, Cebu - Ground Floor Slab Column Works
16 August 2011New Photos added for Ermita, Manila - Structure and Cladding Works at Level 9 & 10
10 August 2011New Photos added for Hat Yai, Songkhla - Sign Goes Up in Hat Yai
09 August 2011New Photos added for Pattaya, Chonburi -Concrete Works Progress to 3rd Floor
08 August 2011New Photos added for Patong, Phuket - Site Demolition Nearing Complete
04 August 2011New Photos added for Angeles City, Pampanga - 4th Floor Concrete Preparatory Works Underway
03 August 2011New Photos added for Makati, Manila - Above Ground Concrete Works Underway
02 August 2011New Photos added for Ermita, Manila - Concrete Works in Progress on 10th Floor
01 August 2011New Photos added for Asoke, Bangkok - Site Clearance and Contractor Mobilisation
28 July 2011New Photos added for Cebu City, Cebu - Basement Concrete Works Continue
27 July 2011New Photos added for Pasar Baru, Jakarta - Piles Exposed for Foundation Works
26 July 2011New Photos added for Pattaya, Chonburi - Above Ground Works Commence
20 July 2011New Photos added for Angeles City, Pampanga - Preparatory Works for Concrete Pouring on 3rd Floor
19 July 2011New Photos added for Makati, Manila - Basement Works Completing
18 July 2011New Photos added for Ermita, Manila - Preparation for Concrete Works on 9th Floor Underway
13 July 2011New Photos added for Pasar Baru, Jakarta - Piling Complete and Foundation Works Commencing
12 July 2011New Photos added for Pattaya, Chonburi - Foundation and Basement Works Completing
11 July 2011New Photos added for Cebu City, Cebu - Ongoing Concrete Works to Below Ground Level
08 July 2011Red Planet closes on a hotel development in Ortigas, Manila
07 July 2011New Photos added for Ermita, Manila - Concrete Works on 7th Floor Commence
05 July 2011New Photos added for Angeles City, Pampanga - Concrete Pouring on Second Floor
04 July 2011New Photos added for Makati, Manila - Basement and Ground Floor Works Continue
30 June 2011New Photos added for Cebu City, Cebu - Ongoing Excavation Works
29 June 2011New Photos added for Hat Yai, Songkhla - Refurbishment Works Continue
28 June 2011New Photos added for Pattaya, Chonburi - Basement Works Nearing Completion
27 June 2011New Photos added for Pasar Baru, Jakarta - Piling Works Progressing Onsite
23 June 2011New Photos added for Ermita, Manila - Main Structure Works Progressed up to 6th Floor
22 June 2011New Photos added for Makati, Manila - Basement and Ground Floor Works Progressing
21 June 2011New Photos added for Angeles City, Pampanga - Reinforcement and Column Works Begin
20 June 2011New Photos added for Makassar, Sulawesi - Site Demolition Works Conclude
16 June 2011New Photos added for Pattaya, Chonburi - Basement Concreting Works Progressing Onsite
13 June 2011New Photos added for Cebu City, Cebu - Excavation Works Continue
13 June 2011New Photos added for Hat Yai, Songkhla - Refurbishment Works Commence
08 June 2011New Photos added for Makati, Manila - Hotel Begins to Emerge out of the Ground
07 June 2011New Photos added for Ermita, Manila - Fifth Storey Completes
06 June 2011New Photos added for Angeles City, Pampanga - Preparatory Foundation Works
31 May 2011New Photos added for Pattaya, Chonburi - Piling Complete & Excavation Work Underway
30 May 2011New Photos added for Cebu City, Cebu - Contractor Starts on Site
26 May 2011New Photos added for Makati, Manila - Basement and Sub-Basement Works Ongoing
25 May 2011New Photos added for Ermita, Manila - Third Storey Emerges
24 May 2011New Photos added for Angeles City, Pampanga - Contractor Mobilises on Site
24 May 2011Red Planet closes on a hotel development in Cagayan de Oro, Mindanao
12 May 2011New Photos added for Makati, Manila - Foundation Pads Ready for Concrete Pouring
11 May 2011New Photos added for Pattaya, Chonburi - Piling Works Now 60% Complete
10 May 2011New Photos added for Pasar Baru, Jakarta - Site Demolition Completed Before Piling
09 May 2011New Photos added for Ermita, Manila - Second Storey Emerges Over the Site Fence
04 May 2011New Photos added for Pattaya, Chonburi - Piling Works Now 40% Complete
28 April 2011New Photos added for Ermita, Manila - First Floor Concrete Slab Works Underway
27 April 2011New Photos added for Surabaya, Java - Geotechnical Investigation
27 April 2011New Photos added for Pattaya, Chonburi - Piling Works Ongoing 25% Complete
26 April 2011New Photos added for Makati, Manila - Soil Protection Works in Progress
11 April 2011Red Planet closes on a hotel development in Hat Yai, Songkhla
11 April 2011New Photos added for Pattaya, Chonburi - The Commencement of Piling Works
11 April 2011New Photos added for Hat Yai, Songkhla - Red Planet has acquired an existing hotel in Hat Yai, Thailand
08 April 2011Red Planet closes on a hotel development in Patong, Phuket
08 April 2011Red Planet closes on a hotel development in Palembang, Sumatra
05 April 2011New Photos added for Ermita, Manila - Update Construction
04 April 2011New Photos added for Pattata, Chonburi - Site Establishment and Setting Out
15 March 2011New Photos added for Ermita, Manila - Tower Crane Installation
10 March 2011New Photos added for Ermita, Manila - Update Construction
09 March 2011New Photos added for Makati, Manila - Update Construction
08 March 2011New Photos added for Pekanbaru, Indonesia - Demolition and Removal of Existing Buildings
02 March 2011New Photos added for Makati, Manila - Update Construction
01 March 2011New Photos added for Ermita, Manila - Update Construction
01 March 2011Job Posting for Philippines
22 February 2011New Photos added for Ermita, Manila - Update Construction
14 February 2011New Photos added for Ermita, Manila - Update Construction
11 February 2011Red Planet closes on a hotel development in Surabaya, Java
07 January 2011Red Planet closes on a hotel development in Pekanbaru, Sumatra
23 December 2010Red Planet closes on a hotel development in Makassar, Sulawesi
29 October 2010New Photos added for Cebu City, Cebu - Site Acquisition
29 October 2010Red Planet closes on a hotel development in Cebu City, Cebu
01 October 2010New Photos added for Ermita, Manila - Site Piling
15 September 2010New Photos added for Angeles City, Pampanga - Site Demolition
13 September 2010New Photos added for Asoke, Bangkok - Site Acquisition
13 September 2010Red Planet closes on a hotel development in Asoke, Bangkok
02 September 2010Red Planet closes on a hotel development in Pasar Baru, Jakarta
02 September 2010New Photos added for Pasar Baru, Jakarta - Site Acquisition
18 August 2010New Photos added for Ermita, Manila - Full Demolition and Site Clearance
11 August 2010New Photos added for Angeles City, Pampanga - Site Acquisition
10 August 2010Red Planet closes on a hotel development in Angeles City, Pampanga
29 July 2010New Photos added for Pattaya, Chonburi - Site Acquisition
29 July 2010Red Planet closes on a hotel development in Pattaya, Chonburi
07 July 2010New Photos added for Makati, Manila - Site Acquisition
07 July 2010Red Planet closes on a hotel development in Makati, Manila
15 June 2010New Photos added for Ermita, Manila - Initial Demolition
01 June 2010New Photos added for Ermita, Manila - Site Acquisition
01 June 2010Red Planet closes on a hotel development in Ermita, Manila